School/□ Systems Engineer/Week 10
Is the code right? Is the model right?
Your simulation of a cooling cup is bug-free and matches the equation perfectly. It is still wrong by 10 °C. How can both be true?
About 35 min · 3 goals · Checked by automated tests
1.Why should I care?
Every engineering simulation can fail in two separate ways: the code can be wrong, or the physics can be wrong. Engineers check both, in that order, and write down which they checked. A model that passes only one is not yet evidence.
- ◇ Define verification (solving the equations correctly) and validation (solving the right equations).
- ◇ Verify a simulation against an exact solution and a step-size convergence check.
- ◇ Validate a model against data that was not used to fit it.
2.Predict
A simulation agrees with the exact solution of its equation to four decimal places. What has that proved?
Guess first. Being wrong here is how the surprise works.
3.Understand
Verification: solving the equations right
Check the code against cases with known answers: an exact solution, a conserved quantity, a limit like 'no input means no change'. Then halve the time step: if the answer still changes noticeably, the step was too big. These checks say nothing about the real world.
Validation: solving the right equations
Compare the model with measurements, ideally from runs not used to fit its parameters. Fitting τ to one cooling curve and then predicting a second cup at a different starting temperature is a real test; matching the curve you fitted to is not.
Order matters, and so does honesty
Verify first: a bug can masquerade as a physics problem. Then validate, report the error, and list the assumptions the model makes (constant room temperature, uniform cup temperature). Saying 'validated for these conditions' is honest; 'validated' alone rarely is.
Explain it another way
Verification asks whether you followed the recipe correctly. Validation asks whether the recipe makes the cake you wanted.
Verification: code-to-model agreement (convergence order, analytic benchmarks, unit tests). Validation: model-to-reality agreement on held-out data, with quantified error and a stated domain of validity.
Every integrator behind this term's diagrams is unit-tested against its closed-form solution: that is verification. None of them has been validated against a real motor or lift, which is why they are called educational models.
Worked example 1
Euler's method on dy/dt = −y/2 from y(0) = 1 gives y(2) = 0.3487 with dt = 0.2 and 0.3660 with dt = 0.02. The exact value is e^(−1) = 0.3679. What does this tell you?
The error falls from 0.019 to 0.0019 when dt shrinks ten times: first-order convergence, as expected for Euler. The code is verified for this case. It says nothing yet about whether dy/dt = −y/2 describes the real system.
Common mix-ups
- If the simulation matches the exact solution, the model is right.
✓ That only verifies the code. The equations can still miss real physics. - A model either is or isn't valid.
✓ Validity has a domain: a cooling model can be good from 80 °C to 40 °C and poor near room temperature.
4.Discover
Investigation: in the feedback lab, set a first-order plant with K = 1, τ = 2 s under P control with Kp = 1 and a set point of 1. Theory says the loop settles at 0.5 with a time constant of 1 s, so y(1 s) ≈ 0.5 × 0.632 = 0.32. Read y at t = 1 s from the plot. If it agrees, you have a verification check; write down what it does not tell you about a real motor.
Explorer 02 — Feedback control
Measure, compare, correct
A controller compares the setpoint with what the sensor reports and pushes the plant to close the gap. Tune the gains and watch speed, overshoot and accuracy trade against each other.
- Setpoint r = 1
- Closed-loop output
- Open loop (u = r/K)
- ±2 % band
Gains
Applies the command the model says is right, u = r / K, without ever measuring.
Plant
Like motor speed or an oven: τ·ẏ = −y + K·u. K = 1.
Real-world effects
Noise only affects the closed loop: the derivative term amplifies it.
- Rise 10–90 %
- 0.72 s
- Overshoot
- 0.0 %
- Settling 2 %
- 1.30 s
- Steady-state err
- 0.333
- theory r/(1+Kp·K) = 0.333
State
P control, Kp 2.0 on a first-order plant with τ 1.0 s. Rise time 0.72 s, overshoot 0.0 %, 2 % settling 1.30 s, steady-state error 0.333 (theory for P: 0.333). Peak control effort 2.00. Open loop: steady-state error 0.000.
P control, Kp 2.0 on a first-order plant with τ 1.0 s. Rise time 0.72 s, overshoot 0.0 %, 2 % settling 1.30 s, steady-state error 0.333 (theory for P: 0.333). Peak control effort 2.00. Open loop: steady-state error 0.000.
How to read this
The top panel shows the setpoint (dashed line at 1) and the plant's true output after a step command at t = 0. The solid line is the controlled system; the dotted line is open loop. The bottom panel shows the control effort u the actuator is asked to deliver.
Rise time is how long the output takes to go from 10 % to 90 % of where it ends up. Overshoot is how far it passes that value. Settling time is when it stays inside ±2 % for good. Steady-state error is the gap left at the end: P control always leaves one on these plants; integral action removes it.
Assumptions & limitations
- Linear plant models with known, constant parameters (K = 1). Real motors and heaters have friction, dead zones and parameters that drift with temperature and wear.
- Controller runs every 10 ms and holds its output between samples; the plant is integrated with 4th-order Runge–Kutta at the same step. There is no transport delay, which real systems almost always have.
- The derivative acts on the measurement (not the error) through a 50 ms low-pass filter, a common practical choice that avoids a spike when the setpoint jumps.
- Sensor noise is white Gaussian and seeded for repeatability; it is added only to the measurement, never to the true output.
- Metrics are computed on the true output up to the disturbance time (or 10 s); a response still moving at the end of the window is reported as not settled.
- Open loop uses the exact plant gain to pick its command. That flatters it: any modelling error would show up as steady-state error.
Can't use the interactive? Read a description instead
In the feedback lab, a first-order plant under P control (K = 1, τ = 2 s, Kp = 1) rises smoothly towards 0.5 and is at about 0.32 after 1 s, matching the formula. That agreement is a verification check.
5.Checkpoint: guided practice
Check what you just discovered before going on. Hints appear after a wrong answer.
Practice 1
You compare your cooling model with a thermometer log from a second cup. Which activity is that?
6.Practice on your own
Practice, not a test. Wrong answers get a hint and another try.
Practice 2
Why validate on data you did not fit to?
Practice 3
Halving the simulation time step changes your answer by 15 %. What should you conclude?
Practice 4
Euler's error for a problem is 0.020 at dt = 0.1 s. Euler's error is proportional to dt. What error do you expect at dt = 0.025 s?
Practice 5 · a fresh version every time
You simulate τ·dy/dt + y = 0 with explicit Euler, τ = 1.5 s. Above what time step dt (in seconds) does the simulation become unstable?
7.Apply it
Write a half-page verification and validation plan for a model of your choice (cooling drink, falling paper cone, charging phone). List two verification checks, one validation dataset you could collect, and the error you would accept.
8.Reflect
Concepts: Simulation and time stepping · First-order systems and the time constant · Overfitting and held-out tests