Lite / Engineering Complex Systems / Week 36
Plan the capstone: requirements, metrics, baselines and budgets
Your capstone has a few weeks and one laptop. What will you claim at the end, and how will you know if it's true?
Why should I care?
The year capstone asks for a quantitative, reproducible systems engineering investigation with a fair baseline and honest limitations. Everything in this term (uncertainty, optimisation, budgets, benchmarking, writing) is a tool for that plan.
- Choose a capstone system and question by screening options against constraints and objectives.
- Write a plan with explicit assumptions, metrics defined before testing, a fair baseline and an uncertainty method.
- Budget the project's own resources (time, computation, scope) with margin.
Predict
Which capstone question is best scoped?
- Make the best robot controller ever
- Does adding integral action to the lift's levelling controller reduce settling error at full load by at least 50% versus P-only, within the comfort limits, in simulation?
- Study elevators
- Prove PID is always optimal
Guess first, then reveal
It names the system, the change, the metric, the threshold, the baseline, the constraints and the setting. You can finish it, measure it, and be wrong in a clear way.
Discover
Use the trade-off lab as a project-selection tool: score candidate capstone ideas against criteria such as feasibility in the time available, measurability, novelty to you, and risk. Change the weights and see which ideas stay on the Pareto front.
What the interactive shows (text version)
The trade-off lab scores options against weighted criteria and marks which are non-dominated. Used for project selection, it shows which capstone ideas remain sensible under different priorities, such as weighting feasibility more heavily than novelty.
Understand
From idea to question
Pick a system you can model and measure (a Build, a simulator, a small program). Write one question with: the change, the metric, the baseline, the conditions and a threshold that would count as success. Screen ideas against hard constraints (time, tools available, safety: browser-based only) before ranking the rest.
Assumptions and metrics first
List the modelling assumptions and the expected effect of each ('no wind: energy likely underestimated'). Define metrics and how they're computed before any test. Decide the uncertainty method (repeats with CI, Monte Carlo over inputs) and the number of runs from the precision you need.
Baseline and ablation plan
Choose the strongest simple baseline and tune it fairly. If your design has several parts, plan the ablation rows now. Pre-register your decision rule in your project log with a date, so you can't move the goalposts later.
Budget the project itself
Treat your time like a mission budget: estimate each task, add contingency (first projects overrun), and keep margin. Plan a minimum viable result by the midpoint, then extensions. Decide in advance what you'll cut if you fall behind. Reproducibility tasks (scripts, seeds, README) go in the budget, not at the end.
Explain it another way
Intuitive
Before a long journey you pick the destination, check the map, pack the essentials, set a turnaround time and leave spare fuel. A capstone plan is the same.
Technical
Plan contents: question, hypothesis, system and version, assumptions, independent and controlled variables, metrics, baseline, statistics, decision rule, ablations, schedule with contingency, risks, reproducibility package.
Applied
Space missions pass formal milestones (concept, preliminary design, critical design) where reviewers check exactly these things: requirements, budgets with margins, verification plans and risks.
Worked example 1
Budget: 30 hours available. Estimates: setup 4, baseline 5, design 8, experiments 6, write-up 5. Contingency 20%. Margin?
Sum 28 h; with 20% contingency 33.6 h. Margin = (30 − 33.6)/33.6 = −11%. Cut scope now: drop one design variant or simplify the ablation, and plan a minimum result by hour 15.
Common mix-ups
A bigger, more ambitious capstone is always better.
✓ A focused question answered rigorously beats a sprawling one answered vaguely.You can decide the metrics once you see what looks good.
✓ Metrics and decision rules are defined before testing, or the evaluation isn't fair.
Practice
Practice, not a test. Answers are checked on our server; a wrong answer gets a hint and another try. Nothing is saved.
Apply it
Write your one-page capstone plan using the headings above: question, assumptions, metrics, baseline, uncertainty method, decision rule, ablations, time budget with margin, and what you'll cut first.
Reflect
What would make you change your capstone question halfway through, and how would you document it?
Write your answer on paper or in your own notes. Lite never stores what you write.