School/□ Systems Engineer/Week 36
Plan the capstone: requirements, metrics, baselines and budgets
Your capstone has a few weeks and one laptop. What will you claim at the end, and how will you know if it's true?
About 45 min · 3 goals · Checked by automated tests
1.Why should I care?
The year capstone asks for a quantitative, reproducible systems engineering investigation with a fair baseline and honest limitations. Everything in this term (uncertainty, optimisation, budgets, benchmarking, writing) is a tool for that plan.
- ◇ Choose a capstone system and question by screening options against constraints and objectives.
- ◇ Write a plan with explicit assumptions, metrics defined before testing, a fair baseline and an uncertainty method.
- ◇ Budget the project's own resources (time, computation, scope) with margin.
2.Predict
Which capstone question is best scoped?
Guess first. Being wrong here is how the surprise works.
3.Discover
Use the trade-off lab as a project-selection tool: score candidate capstone ideas against criteria such as feasibility in the time available, measurability, novelty to you, and risk. Change the weights and see which ideas stay on the Pareto front.
Explorer 04 — Engineering constraints
No design wins on everything
Choosing a robot's perception and compute stack means trading cost, power and capability. Set your priorities and limits, then see which options survive and which are simply worse than another.
- Meets limits
- ✕ Violates a limit
- Pareto frontier
- Outside a limit
Limits
Priorities (weights 0–10)
Cheaper is better
Lower draw means a smaller battery or longer run time
Headroom for heavier algorithms later
Estimated task success
Illustrative figures for teaching, not measured specifications
BMicrocontroller + low-res cameraRank 1
Microcontroller reading a small low-resolution camera for colour blobs.
- Cost
- 30 CU
- Power
- 0.9 W
- Compute
- 3×
- Est. accuracy
- 52 %
✓ Meets all limits · On the frontier
Score58DSBC + cameraRank 2
Single-board computer running classical vision on a standard camera.
- Cost
- 80 CU
- Power
- 5.5 W
- Compute
- 25×
- Est. accuracy
- 74 %
✓ Meets all limits · On the frontier
Score57AMicrocontroller onlyRank 3
Microcontroller with distance and contact sensors; no camera.
- Cost
- 12 CU
- Power
- 0.3 W
- Compute
- 1×
- Est. accuracy
- 35 %
✓ Meets all limits · On the frontier
Score50CSingle-board computerRank 4
General-purpose single-board computer with the same simple sensors, no camera.
- Cost
- 55 CU
- Power
- 4.0 W
- Compute
- 25×
- Est. accuracy
- 48 %
✓ Meets all limits · Dominated by B (no worse on cost or accuracy, better on one)
Score46ESBC + camera + acceleratorExcluded
Adds a neural-network accelerator for learned object detection.
- Cost
- 150 CU
- Power
- 10.0 W
- Compute
- 120×
- Est. accuracy
- 86 %
✕ over budget by 50 CU; over power limit by 2 W · On the frontier
Score53FSBC + depth cameraExcluded
Single-board computer with a depth camera; better 3-D estimates, costly sensor.
- Cost
- 165 CU
- Power
- 7.5 W
- Compute
- 25×
- Est. accuracy
- 82 %
✕ over budget by 65 CU · Dominated by E (no worse on cost or accuracy, better on one)
Score42
State
4 of 6 options meet the limits (budget 100 CU, power 8.0 W). Highest weighted score: B, Microcontroller + low-res camera, 58 of 100, on the Pareto frontier. Frontier on cost versus accuracy: A, B, D, E.
4 of 6 options meet the limits (budget 100 CU, power 8.0 W). Highest weighted score: B, Microcontroller + low-res camera, 58 of 100, on the Pareto frontier. Frontier on cost versus accuracy: A, B, D, E.
How to read this
Each circle is a design option, placed by cost (left is better) and estimated accuracy (up is better); its area shows power. Filled circles meet every limit you set; dashed, hollow circles marked ✕ break at least one, and the hatched area shows where a limit rules options out.
The stepped line is the Pareto frontier: options for which nothing else is both cheaper (or lower-power) and more accurate. An option off the frontier is dominated, meaning another option beats it on both axes, whatever your priorities. The weighted score below is a different question: it depends entirely on the weights you chose, so two people can reasonably rank the frontier differently.
Assumptions & limitations
- All figures are illustrative teaching values chosen to make trade-offs visible. They are not measured specifications, prices or benchmarks of any product.
- Options are generic archetypes; real stacks vary widely in what each part costs, draws and achieves.
- Scores use a weighted sum of min–max normalised criteria. Normalisation is relative to these six options, so adding or removing one changes every score.
- A weighted sum hides trade-offs: a high score can come from one extreme strength. That is why the Pareto view is shown alongside it.
- The frontier is computed on the two plotted criteria only; an option dominated here may still be the best on a criterion not plotted (for example F has lower power than E).
- Accuracy is treated as a single fixed number. In practice it depends on lighting, the objects, the algorithm and integration effort, and is uncertain until tested.
Can't use the interactive? Read a description instead
The trade-off lab scores options against weighted criteria and marks which are non-dominated. Used for project selection, it shows which capstone ideas remain sensible under different priorities, such as weighting feasibility more heavily than novelty.
4.Checkpoint: guided practice
Check what you just discovered before going on. Hints appear after a wrong answer.
Practice 1
Which element is missing from: 'Does PI control reduce greenhouse energy use?'
5.Understand
From idea to question
Pick a system you can model and measure (a Build, a simulator, a small program). Write one question with: the change, the metric, the baseline, the conditions and a threshold that would count as success. Screen ideas against hard constraints (time, tools available, safety: browser-based only) before ranking the rest.
Assumptions and metrics first
List the modelling assumptions and the expected effect of each ('no wind: energy likely underestimated'). Define metrics and how they're computed before any test. Decide the uncertainty method (repeats with CI, Monte Carlo over inputs) and the number of runs from the precision you need.
Baseline and ablation plan
Choose the strongest simple baseline and tune it fairly. If your design has several parts, plan the ablation rows now. Pre-register your decision rule in your project log with a date, so you can't move the goalposts later.
Budget the project itself
Treat your time like a mission budget: estimate each task, add contingency (first projects overrun), and keep margin. Plan a minimum viable result by the midpoint, then extensions. Decide in advance what you'll cut if you fall behind. Reproducibility tasks (scripts, seeds, README) go in the budget, not at the end.
Explain it another way
Before a long journey you pick the destination, check the map, pack the essentials, set a turnaround time and leave spare fuel. A capstone plan is the same.
Plan contents: question, hypothesis, system and version, assumptions, independent and controlled variables, metrics, baseline, statistics, decision rule, ablations, schedule with contingency, risks, reproducibility package.
Space missions pass formal milestones (concept, preliminary design, critical design) where reviewers check exactly these things: requirements, budgets with margins, verification plans and risks.
Worked example 1
Budget: 30 hours available. Estimates: setup 4, baseline 5, design 8, experiments 6, write-up 5. Contingency 20%. Margin?
Sum 28 h; with 20% contingency 33.6 h. Margin = (30 − 33.6)/33.6 = −11%. Cut scope now: drop one design variant or simplify the ablation, and plan a minimum result by hour 15.
Common mix-ups
- A bigger, more ambitious capstone is always better.
✓ A focused question answered rigorously beats a sprawling one answered vaguely. - You can decide the metrics once you see what looks good.
✓ Metrics and decision rules are defined before testing, or the evaluation isn't fair.
6.Practice on your own
Practice, not a test. Wrong answers get a hint and another try.
Practice 2 · a fresh version every time
A lander power budget has current best estimates of 51 W, 16 W, 14 W, 50 W. Policy adds 30% contingency to the total. The power system can supply 138 W. Margin = (capability − estimate with contingency) ÷ (estimate with contingency) × 100. What is the margin, in %? (1 decimal place; negative means over budget.)
Practice 3 · a fresh version every time
A sensor's readings have standard deviation σ ≈ 4 units. How many repeated readings n do you need so that the 95% confidence interval for the mean has a half-width of at most 1.5 units? Use z = 1.96 and round n up to a whole number.
Practice 4
Why write your decision rule in your log before running experiments?
7.Apply it
Write your one-page capstone plan using the headings above: question, assumptions, metrics, baseline, uncertainty method, decision rule, ablations, time budget with margin, and what you'll cut first.
8.Reflect
Concepts: Experimental design and test protocols · Benchmarking methodology · Pareto fronts and multi-objective trade-offs · Constraints, budgets and trade-offs