Reading a step response like an engineer

Two controllers both reach the set point. One is twice as good. Which four numbers would prove it?

About 30 min · 3 goals · Checked by automated tests · Full interactive version

Why should I care?

'It looks better' isn't evidence. Step-response metrics turn a curve into numbers you can write in a specification, compare across designs and check automatically. Every control datasheet speaks this language.

Predict

A response settles at 2.0 and peaks at 2.5. What is its percent overshoot?

  1. 5 %
  2. 20 %
  3. 25 %
  4. 50 %
Guess first, then reveal

Overshoot = (peak − final)/final = 0.5/2.0 = 25 %. Always measure relative to the final value, not the set point, unless the spec says otherwise.

Discover

In the feedback lab, pick a second-order plant with PI control. Read rise time (10–90 %), overshoot, peak time and 2 % settling time off the plot by hand. Then compare with the lab's own readout and explain any differences.

What the interactive shows (text version)

A second-order PI-controlled response rises past the set point, peaks, oscillates a little and settles. Rise time is measured between the 10 % and 90 % crossings, overshoot as the peak's excess over the final value, and settling time as the moment after which it stays within 2 % of the final value.

You can also open the interactive on the full site when you have a faster connection.

Watch (optional)

Watch for: Write down each metric the video defines and the convention it uses (for example, which percentage band defines settling).

What rise time, overshoot and settling time actually tell an engineer, and why the step is the standard test input.

“The Step Response | Control Systems in Practice” by MATLAB (opens YouTube; streaming video uses a lot of data)

The video is optional. Everything you need is in this lesson's text.

Understand

The five numbers

Rise time: from 10 % to 90 % of the final value. Peak time tp: when the first maximum occurs. Percent overshoot: (peak − final)/final × 100. Settling time ts: after this, the response stays within ±2 % (sometimes 5 %) of final. Steady-state error: set point minus final value.

Conventions are part of the number

'Settling time 3 s' means nothing without the band: 2 % and 5 % can differ by a factor of 1.3. Rise time may be 0–100 % or 10–90 %. Good reports state the convention once, then use it everywhere.

Metrics pull against each other

Faster rise usually means more overshoot. Less overshoot often means slower settling. Removing steady-state error with integral action can add overshoot. A specification lists limits on several metrics at once, so a design is judged on the whole set.

Explain it another way

Intuitive

Rise time: how quickly you get there. Overshoot: how far past you go. Settling: how long until you stop wobbling. Steady-state error: whether you ever really arrive.

Technical

For a standard underdamped second-order system: tp = π/ωd, %OS = 100·exp(−ζπ/√(1 − ζ²)), ts(2 %) ≈ 4/(ζωn), rise time (10–90 %) ≈ (1 − 0.4167ζ + 2.917ζ²)/ωn (an empirical fit).

Applied

In the Elevator build, overshoot is literally millimetres past the floor and settling time is how long until the doors can open. Comfort limits add two more metrics: acceleration and jerk.

Worked example 1

A log shows: final value 1.00, first peak 1.12 at t = 0.8 s, inside 0.98–1.02 for good from t = 2.4 s, crossing 0.1 at 0.15 s and 0.9 at 0.45 s. Give the metrics.

Rise time = 0.45 − 0.15 = 0.30 s. Peak time 0.8 s. Overshoot 12 %. 2 % settling time 2.4 s. Steady-state error 0 if the set point was 1.00.

Common mix-ups

Practice

Practice, not a test. Answers are checked on our server; a wrong answer gets a hint and another try. Nothing is saved.

%

s

Practice 3. Design A settles in 2.1 s (5 % band). Design B settles in 2.6 s (2 % band). Which is faster?

s

Practice 5. A response settles at 0.95 when the set point is 1.0. What does that tell you?

Apply it

Write a one-paragraph specification for a robot joint's step response using at least four metrics with numbers and conventions. Then test one configuration in the feedback lab and report pass or fail for each line.

Reflect

Which metric would a passenger in a lift care about most, and which would the building manager care about?

Write your answer on paper or in your own notes. Lite never stores what you write.

← Taming a shaking drumFrom overshoot to ζ and back →