Scientific methodology
Baselines and control conditions
Also called: baseline · control group · control condition · ablation
Definition
A baseline is the reference condition a new idea is compared with, such as the existing design or a simple method, tested in the same way.
Picture it
'Our new controller reaches the target in 1.2 s' means nothing until you know the old one took 1.3 s, or 3 s. A good baseline is the strongest simple alternative, not a deliberately weak straw man. Ablations remove one part at a time to see what each contributes.
The maths
improvement = (baseline − new) / baseline × 100 (for times or errors)
| Quantity | Unit | Symbol |
|---|---|---|
| percentage | per cent | % |
Worked example
A baseline line-follower completes a course in 42 s on average and a new version in 35 s. What is the percentage improvement?
- (42 − 35) / 42 × 100 = 7 / 42 × 100 = 16.7 %
AnswerAbout 16.7 % faster than the baseline.
✓ The number in this answer is recomputed from scratch by an automated test.
Common misconceptions
- Misconception: Comparing against a weak baseline exaggerates the benefit.
- Misconception: Baseline and new version must be tested under the same conditions and in an interleaved order.