TactivergeLite

Lite / Independent Engineering Research / Week 12

Error budgets: where does the uncertainty come from?

A landing has six independent sources of position error. Halving the smallest one saves almost nothing. Halving the biggest saves a lot. How do you know which is which?

About 35 min · 3 goals · Checked by automated tests · Full interactive version

Why should I care?

Big engineering programmes manage uncertainty with budgets, just like mass and power. Each subsystem is given an allowance; the budget shows where effort pays. It is the bridge from statistics to design decisions.

Predict

Three independent errors: 3 m, 4 m and 1 m (1σ). Roughly what is the total?

  1. 8 m
  2. 5.1 m
  3. 4 m
  4. 12 m
Guess first, then reveal

√(9 + 16 + 1) = √26 ≈ 5.1 m. The 1 m term changes the total by only 0.1 m: small terms nearly vanish in a root-sum-square.

Discover

In the fusion lab, set the filter to Kalman and record the position RMSE with default settings. Then change one error source at a time (camera noise, odometry noise, odometry bias, dropout) by a factor of two and record the new RMSE. Rank the sources by how much they matter: that is an empirical error budget.

What the interactive shows (text version)

The fusion lab experiment can be recorded as a table: error source, its setting, and the resulting RMSE. The ranking comes from the numbers, not the plot.

You can also open the interactive on the full site when you have a faster connection.

Understand

Root-sum-square

If contributions eᵢ are independent with standard deviations σᵢ, the total σ = √(Σσᵢ²). Squares make the big terms dominate: a term half the size of the largest contributes only a quarter as much variance.

Sensitivity and payoff

∂σ/∂σᵢ = σᵢ/σ. Improving the largest term pays most. A good budget lists each term, its source, how it was estimated (test, analysis, data sheet) and its share of total variance σᵢ²/σ².

Allocation and margin

Work backwards from a requirement: if the landing must be within 10 km (3σ), the total 1σ must be ≤ 3.3 km. Allocate that among subsystems so the RSS fits, keeping margin for errors not yet understood. Correlated terms must be combined with their covariance, or added linearly as a conservative bound.

Explain it another way

Intuitive

Errors are like noise from several loudspeakers at once. The loudest speaker sets how noisy the room is; turning down the quiet ones barely helps.

Technical

This is variance decomposition. For nonlinear systems the same idea is done with Monte Carlo and sensitivity indices (such as Sobol indices) instead of a simple sum.

Mathematical

Budget 2, 6, 5, 1.5 km: total = √(4 + 36 + 25 + 2.25) = √67.25 ≈ 8.20 km. Halving the 6 km term: √(4 + 9 + 25 + 2.25) ≈ 6.34 km. Halving the 1.5 km term: √(4 + 36 + 25 + 0.5625) ≈ 8.10 km.

Applied

Mars landing ellipses are built from such budgets: entry navigation, atmosphere density, aerodynamics and timing each contribute, and the dominant term has historically driven the next mission's technology choices.

Worked example 1

Contributions 2, 6, 5 and 1.5 km. Total, and the share of variance from the 6 km term?

Total = √67.25 ≈ 8.20 km. Share = 36/67.25 ≈ 54%.

Common mix-ups

Practice

Practice, not a test. Answers are checked on our server; a wrong answer gets a hint and another try. Nothing is saved.

km

%

m

Practice 4. A budget has terms 1, 2 and 8 m. You can halve any one term. Which gives the biggest improvement?

Apply it

Write a four-line error budget for the rover's position after a 40 m drive (odometry noise, slip bias, heading error, camera fix). Estimate each term from this term's lessons or the fusion lab, give the total, and say which one you would attack first.

Reflect

What would make you add two error terms linearly instead of in quadrature?

Write your answer on paper or in your own notes. Lite never stores what you write.

Go further

Research mode: limits and open questions

In your term project, an error budget is a strong way to explain WHY one estimator beats another: which error source it suppresses.

← Propagating uncertainty: linearisation and Monte CarloBayes' rule for sensor readings →