Definition

A bill of materials lists every part needed to build something, with quantity, exact part number or specification, supplier and cost.

Picture it

A BOM is what turns 'I built a robot' into 'you can build this robot'. Specific matters: '10 kΩ resistor, 0.25 W, 5 %' rather than 'resistor'. Totals let you budget and spot the expensive line worth redesigning.

The maths

total cost = Σ (quantity × unit cost)
SI units used in this entry
QuantityUnitSymbol
ratiodimensionless1

Worked example

A BOM lists 2 motors at 6.50 each, 4 wheels at 1.25 each, 1 controller at 12.00 and 20 screws at 0.05 each (any currency). What is the total, and which line costs most?

  1. Motors: 2 × 6.50 = 13.00
  2. Wheels: 4 × 1.25 = 5.00
  3. Controller: 12.00
  4. Screws: 20 × 0.05 = 1.00
  5. Total = 31

Answer31.00 in total; the motors line (13.00) is the largest.

✓ The 2 numbers in this answer are recomputed from scratch by an automated test.

Common misconceptions

  • Misconception: Leaving out 'small' parts such as screws and wire makes a BOM unusable for rebuilding.
  • Misconception: A BOM without versions or part numbers goes stale when suppliers change parts.