Bills of materials and reproducibility
How to list exactly what a design is made of so someone else can build the same thing, with a worked example BOM and the details that make it reproducible.
Lesson 4 of 6 · 25 min · Self-paced · Free
"It works on mine"
Two students build the same gripper from the same drawings. One grips well; the other's fingers slip and its motor stalls. After a week of puzzling, they discover that one used screws of a slightly different length, a softer fingertip material and a motor that looked identical but had less torque. The drawings were the same. The materials were not.
A design is only reproducible if you know precisely what it is made of. The document that records this is the bill of materials, or BOM: a structured list of every part, material and quantity needed to build one unit of a design.
What goes in a BOM
A useful BOM has one row per distinct part and, at minimum, these columns:
- Item number: a simple label (1, 2, 3…) that assembly instructions and drawings can refer to.
- Quantity per assembled unit.
- Description: what the part is, in plain words.
- Specification: exactly enough detail that someone could buy or make the same thing. This is the column that makes or breaks reproducibility.
- Source: where it comes from — bought, made in-house from a drawing, or included with another part.
- Unit cost and line cost (quantity × unit cost), if cost matters.
- Notes: substitutes that are known to work, things to watch out for.
Professional BOMs often add a manufacturer part number, a supplier part number, and for electronics a reference designator — the label on the circuit diagram such as R1 for the first resistor or C3 for the third capacitor — so each row can be matched to a place on the board.
Specifications: say exactly what you mean
Compare these descriptions of the same part:
- "Screw"
- "Small screw"
- "M3 × 10 mm socket head cap screw, stainless steel"
Only the last one can be reproduced. In the metric system, M3 means a nominal thread diameter of 3 mm, and the 10 mm is the length. "Socket head" says what tool drives it. "Stainless steel" says what it is made of. Similar care applies to everything: a sheet material needs its thickness and type, a printed part needs its file name and version, an electronic part needs its key ratings.
When you cannot give a unique product, give the properties that matter. If the design depends on a motor producing a certain torque, write the required torque in the specification, not just "small motor". Then anyone substituting a different part can check whether it meets the requirement.
A worked example BOM
BOMs are usually kept as spreadsheets, and the simplest portable format is CSV (comma-separated values): plain text, one row per line, columns separated by commas. Any spreadsheet program can open it, and version control can track changes to it line by line.
Here is a BOM for a hypothetical two-finger gripper. The design, part choices and prices are all made up for illustration; real prices vary widely.
item,qty,description,specification,source,unit_cost,line_cost,notes
1,1,Base plate,PLA printed part per base_plate_v3.step,make,0.80,0.80,material cost only
2,2,Finger,PLA printed part per finger_v5.step,make,0.40,0.80,print with flat face down
3,2,Fingertip pad,silicone sheet 2 mm thick cut to 15 x 25 mm,buy,0.25,0.50,softer pads grip better on smooth objects
4,1,Gripper actuator,micro servo 5 V with metal gears; at least the torque given in docs/sizing.md,buy,4.50,4.50,check torque before substituting
5,4,Machine screw,M3 x 10 mm socket head cap screw stainless,buy,0.10,0.40,
6,4,Hex nut,M3 stainless,buy,0.05,0.20,
7,1,Actuator horn,supplied with item 4,included,0.00,0.00,The total cost is the sum of the line costs:
0.80 + 0.80 + 0.50 + 4.50 + 0.40 + 0.20 + 0.00 = 7.20 (made-up currency units)Check one line yourself: item 5 is 4 screws at 0.10 each, so its line cost is 4 × 0.10 = 0.40.
Notice several details. Printed parts point to a specific file and version (finger_v5.step), so nobody accidentally prints an old finger. The actuator row says what property matters and where the requirement is written. Item 7 appears even though it costs nothing, because an assembler needs to know it exists. And the notes column passes on hard-won knowledge.
Levels: assemblies inside assemblies
Bigger designs are built from sub-assemblies. A robot arm might consist of a base, two joint modules and a gripper, and each of those has its own parts. Engineers handle this with a multi-level (indented) BOM: the top level lists the sub-assemblies, and each sub-assembly has its own BOM. In plain text, a level number is a simple way to show this:
level,item,qty,description
0,A,1,Robot arm (complete)
1,A1,1,Base assembly
1,A2,2,Joint module
2,A2.1,1,Joint housing
2,A2.2,1,Joint actuator
1,A3,1,Gripper assembly (see gripper BOM above)Quantities multiply down the levels: two joint modules, each with one actuator, means two joint actuators in total.
Reproducibility is more than parts
A BOM tells you what. To rebuild the same thing, people also need:
- Versions of everything. The BOM itself should have a version and date, and should match a specific version of the drawings and code.
- Software dependencies. Code has a BOM too: the libraries it uses and their exact versions. In Python, a
requirements.txtfile listing lines such asnumpy==1.26.4pins an exact version, so the program behaves the same on another computer. - Process details. How parts are made matters: print settings, cutting method, the order of assembly, how tight to make the screws.
- Known substitutions. If you tried an alternative part and it failed, say so — that saves the next builder a week.
Project
Paper project: write a BOM for an everyday object
Choose a simple object you can examine without taking it apart or using tools — a stapler, a clipboard, a ring binder, a wooden ruler, or a paper or cardboard model you built yourself.
Write a CSV bill of materials for it with the columns from this lesson. Where you cannot know an exact specification, describe the properties that matter (size, material, thickness) and mark the row as estimated. Estimate made-up unit costs and calculate the total, showing your working.
Finally, swap BOMs with a friend: can they picture every part from your specifications alone?
Deliverables
- A CSV BOM with item, qty, description, specification, source, unit_cost, line_cost and notes
- A total cost with the line-cost working shown, labelled as estimated
- A note of any specifications your friend found unclear, and your fixes